CB-4 initial delivery expected

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

This claim was marked delayed on October 9, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2026-09-16
Promised by
2026-09-30
Current status
delayed

What the later record shows

The date slipped

No passage reports initial CB-4 delivery. As of 2026-10-03, the 336 MW at Lake Mariner (CB-4 and CB-5) was still described as under construction, which is past the late-September target.

“Another 336 MW of critical IT capacity is under construction at Lake Mariner through CB-4 and CB-5.”
2026-09-22 · Rothschild Redburn starts TeraWulf at Neutral, $15 target implies 11.8% downside - Yahoo Finance View cached copy (2026-09-29)Live source ↗
“TeraWulf operates the Lake Mariner Data Campus in New York with 102 MW of revenue-generating critical IT capacity and 336 MW under construction”
2026-10-03 · Terawulf (WULF) Stock Price, News & Analysis - 24/7 Wall St. View cached copy (2026-10-08)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Initial CB-4 delivery expected in late September 2026

Source (primary)

WULF Stock Forecast 2030: TeraWulf Model & Cash Flow - Northwise (-, news_article)
View cached copy (2026-09-20)Live source ↗

Quote: “management's broader milestones of initial CB-4 delivery in late September”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The report describes management's milestone of initial CB-4 delivery in late September, in the context of the 2026 Lake Mariner build-out. The individual hall dates are Northwise's own assumptions, but the claim covers only management's broader milestone.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://northwiseproject.com/research/wulf-stock-forecast-2030) in full (77,288 characters, retrieved September 20, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WULF Stock Forecast 2030: TeraWulf Model & Cash Flow - Northwise

Quote: “management's broader milestones of initial CB-4 delivery in late September”

View cached copy (2026-09-20)Live source ↗

delays Rothschild Redburn starts TeraWulf at Neutral, $15 target implies 11.8% downside - Yahoo Finance

Quote: “Another 336 MW of critical IT capacity is under construction at Lake Mariner through CB-4 and CB-5.”

View cached copy (2026-09-29)Live source ↗

delays Terawulf (WULF) Stock Price, News & Analysis - 24/7 Wall St.

Quote: “TeraWulf operates the Lake Mariner Data Campus in New York with 102 MW of revenue-generating critical IT capacity and 336 MW under construction”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 20, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 1, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — delayed