Fluidstack exclusivity on CB-5
Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory
What the later record shows
Delivered on time · happened August 17, 2025
Within the 30-day exclusivity window, an 8-K dated August 17, 2025 announced a signed CB-5 lease with Fluidstack for more than 160 MW of critical IT load. The September materials state that Fluidstack exercised the option.
“had entered into a Datacenter Lease Agreement for colocation building number 5 (“CB-5”) (the “Fluidstack Lease”) with Fluidstack USA I Inc.”
2025-08-17 · TeraWulf 8-K filed 2025-08-18 View cached copy (2026-08-31)Live source ↗
“Fluidstack has exercised the option to sign CB-5, adding 160+ MW of Critical IT Load”
2025-09-04 · WULF Expands Fluidstack Deal View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Fluidstack has 30-day exclusivity for CB-5, which could add a potential 160 MW of critical IT load.
Source (primary)
terawulf 8-K exhibit (tm2523008d2_ex99-2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-06)Live source ↗
Quote: “Fluidstack has 30 - day exclusivity for CB - 5, adding potential 160 MW Critical IT Load”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The deal presentation states that Fluidstack has 30-day exclusivity for CB-5, which would add a potential 160 MW of critical IT load. This matches the claim exactly.
Confirmed in the source:
- Fluidstack has 30-day exclusivity for CB-5
- CB-5 could add a potential 160 MW of critical IT load
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000110465925078084/tm2523008d2_ex99-2.htm) in full (7,456 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (tm2523008d2_ex99-2.htm)
Quote: “Fluidstack has 30 - day exclusivity for CB - 5, adding potential 160 MW Critical IT Load”
confirms TeraWulf 8-K filed 2025-08-18
Quote: “had entered into a Datacenter Lease Agreement for colocation building number 5 (“CB-5”) (the “Fluidstack Lease”) with Fluidstack USA I Inc.”
confirms WULF Expands Fluidstack Deal
Quote: “Fluidstack has exercised the option to sign CB-5, adding 160+ MW of Critical IT Load”