Company: TeraWulf - Project: Akela Data
The claim, verbatim
Somerset-Brookings leases grant access to up to 750 MW of power and infrastructure equipment at Lake Mariner site
Source (primary)
TeraWulf 8-K filed 2025-08-14 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “grant the respective tenants access to power and infrastructure equipment for up to 750 MW at the Lake Mariner site”
How we checked this
Checked on September 17, 2026. The cited source supports every part of this claim.
The filing states that the leases grant tenants access to power and infrastructure equipment for up to 750 MW at the Lake Mariner site.
Confirmed in the source:
- The Somerset-Brookings Leases, together with the Second A&R Lease, grant tenants access to power and infrastructure equipment
- The access covers up to 750 MW
- The access is at the Lake Mariner site
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1083301/000110465925078086/tm2523008d1_8k.htm) in full (13,360 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms TeraWulf 8-K filed 2025-08-14
Quote: “grant the respective tenants access to power and infrastructure equipment for up to 750 MW at the Lake Mariner site”