Akela Data
Project of TeraWulf
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | -- | ||
| Contracted a customer is on the hook | 378 MW IT load | 2026-09-01 | Akela - Fluidstack Data Center Lease - 378 MW |
| Under construction | 450 MW | 2026-09-01 | Akela data center phased online delivery |
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 750 MW | 2025-08-13 | Somerset-Brookings power and infrastructure capacity |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
2024-12-03
Core42 - tenant · 72.5 MW source
2025-08-13
Fluidstack - tenant · 378 MW · 10-year term source
2025-08-13
Google - guarantor source
Claims about this project
2024-12-03 - stated
2025-05-08 - stated
Core42 long-term HPC hosting lease 72.5 MW.
2025-05-08 - stated
2025-05-08 - stated
2025-05-08 - delayed
2025-05-08 - stated
2025-05-26 - stated
Somerset data center acreage 162.7 acres.
2025-05-26 - stated
Somerset lease annual rent commitment 281398.2 USD.
2025-05-26 - stated
Somerset NY data center lease term 35.0 years.
2025-08-13 - stated
2025-08-13 - stated
Somerset-Brookings leases acreage 162.7 acres.
2025-08-13 - stated
Fluidstack 10-year AI hosting agreement 200.0 MW.
2025-08-13 - stated
Warrant issuance to Google 41011803.0 shares.
2025-08-13 - stated
2025-08-13 - delayed
2025-08-13 - stated
2025-08-13 - stated
2025-08-13 - stated
2025-08-13 - stated
2025-08-14 - stated
Lake Mariner CB-5 lease expansion 160.0 MW.
2025-08-17 - stated
2025-08-17 - stated
CB-5 IT load capacity 160.0 MW.
2025-08-17 - stated
CB-5 construction completion. Promised by 2026-12-31.
2025-08-17 - stated
2025-08-17 - stated
Google warrant issuance 32568197.0 shares.
2026-02-26 - stated
2026-02-26 - stated
Akela Fluidstack lease agreements 378.0 MW.
2026-02-26 - stated
Akela Fluidstack lease for 378 MW 378.0 MW.
2026-02-26 - stated
2026-02-26 - stated
2026-02-26 - stated
2026-02-26 - stated
2026-04-13 - stated
Fluidstack data center lease commitment 378.0 MW.
2026-04-13 - stated
2026-04-14 - stated
Fluidstack data center leases 378.0 MW.
2026-04-15 - stated
Fluidstack data center lease 378.0 MW.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
Akela project data centre capacity 450.0 MW.
2026-09-01 - stated
2026-09-01 - stated