jain.com

Delivery and installation of 18,500 S19j XP miners at Lake Mariner

Company: TeraWulf

Subject kind
facility timeline
Statement date
2023-11-12
Promised by
2023-12-31
Promised amount
18500.0 units
Current status
verified

What the later record shows

Delivered late

The 10-K fleet list as of Dec 31, 2023 shows no S19j XP miners among owned units, and only 4,800 hosted miners, too few to cover 18,500, so the December 2023 target was missed. By Sep 30, 2024 the fleet included 19,400 S19j XP miners, but no passage gives the exact installation date.

“As of December 31, 2023, we owned approximately 30,100 miners, exclusive of the 4,800 hosted miners, of which approximately 28,300 are operational at the Lake Mariner Facility”
2024-03-19 · TeraWulf 10-K filed 2024-03-20 View cached copy (2026-09-13)Live source ↗
“Bitmain S19j XP 19,400 Bitmain S19k Pro 4,100 Bitmain S21 5,100 Bitmain S21 Pro 5,000 58,400 As of September 30, 2024”
2024-11-11 · TeraWulf 10-Q filed 2024-11-12 View cached copy (2026-08-31)Live source ↗

Checked November 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

18,500 Antminer S19j XP miners, about 2.8 EH/s combined, are targeted to be delivered and installed at the Lake Mariner facility in December 2023.

Source (primary)

terawulf 8-K exhibit (wulfq323earningsprfinal1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-17)Live source ↗

Quote: “which are targeted to be delivered and installed at the Lake Mariner facility in December 2023”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (wulfq323earningsprfinal1.htm)

Quote: “which are targeted to be delivered and installed at the Lake Mariner facility in December 2023”

View cached copy (2026-11-17)Live source ↗

confirms TeraWulf 10-Q filed 2024-11-12

Quote: “Bitmain S19j XP 19,400 Bitmain S19k Pro 4,100 Bitmain S21 5,100 Bitmain S21 Pro 5,000 58,400 As of September 30, 2024”

View cached copy (2026-08-31)Live source ↗

confirms TeraWulf 10-K filed 2024-03-20

Quote: “As of December 31, 2023, we owned approximately 30,100 miners, exclusive of the 4,800 hosted miners, of which approximately 28,300 are operational at the Lake Mariner Facility”

View cached copy (2026-09-13)Live source ↗

Record of changes

November 17, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 17, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.