Lake Mariner Building 4 completion by mid-2024

Company: TeraWulf - Project: Akela Data

Subject kind
facility timeline
Statement date
2024-03-05
Promised by
2024-06-30
Promised amount
35.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

Building 4 was meant to take Lake Mariner from 160 MW to 195 MW. Lake Mariner was still at 160 MW on May 31, 2024, and a later chart shows 195 MW by 3Q 2024, so it was finished, but nothing shows whether that happened by June 30.

“increase the facility’s bitcoin mining infrastructure capacity from its current 160 MW to 195 MW by mid 2024”
2024-05-12 · terawulf 8-K exhibit (aex991xearningsreleasexq12.htm) View cached copy (2026-11-06)Live source ↗
“As of May 31, 2024, TeraWulf's operational infrastructure capacity comprised 160 MW at the Lake Mariner facility and 50 MW at the Nautilus facility”
2024-06-03 · terawulf 8-K exhibit (wulfmay24opsreportdraft0.htm) View cached copy (2026-11-04)Live source ↗
“195 MW 195 MW 30 MW 110 MW 60 MW 60 MW 0.3 EH/s 3 MW 1H 2022 2H 2022 1H 2023 2H 2023 3Q 2024 4Q 2024 1Q 2025”
2025-05-08 · Investor Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked November 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Construction of Building 4 at Lake Mariner is substantially funded and on track for completion by mid-2024. It will add 35 MW of capacity and raise operational mining capacity to about 10 EH/s.

Source (primary)

terawulf 8-K exhibit (wulf23resultsand24outloo.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-09)Live source ↗

Quote: “Construction of Building 4 at the Lake Mariner facility is proceeding as planned, substantially funded, and is on track for completion by mid-2024. This additional infrastructure is anticipated to add an incremental 35 MW of capacity”

How we checked this

Checked on November 11, 2026. The cited source supports every part of this claim.

TeraWulf's March 6, 2024 press release states the funding status, mid-2024 completion target, 35 MW addition and approximately 10 EH/s capacity. These were company expectations at that date, and the document does not show whether they were later achieved.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330124000053/wulf23resultsand24outloo.htm) in full (18,117 characters, retrieved November 9, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (wulf23resultsand24outloo.htm)

Quote: “Construction of Building 4 at the Lake Mariner facility is proceeding as planned, substantially funded, and is on track for completion by mid-2024. This additional infrastructure is anticipated to add an incremental 35 MW of capacity”

View cached copy (2026-11-09)Live source ↗

confirms Investor Presentation

Quote: “195 MW 195 MW 30 MW 110 MW 60 MW 60 MW 0.3 EH/s 3 MW 1H 2022 2H 2022 1H 2023 2H 2023 3Q 2024 4Q 2024 1Q 2025”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms terawulf 8-K exhibit (wulfmay24opsreportdraft0.htm)

Quote: “As of May 31, 2024, TeraWulf's operational infrastructure capacity comprised 160 MW at the Lake Mariner facility and 50 MW at the Nautilus facility”

View cached copy (2026-11-04)Live source ↗

confirms terawulf 8-K exhibit (aex991xearningsreleasexq12.htm)

Quote: “increase the facility’s bitcoin mining infrastructure capacity from its current 160 MW to 195 MW by mid 2024”

View cached copy (2026-11-06)Live source ↗

Record of changes

November 9, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.