Fluidstack termination right on Akela Project delay
Company: TeraWulf - Project: Akela Data
The claim, verbatim
Fluidstack may terminate the lease for an Akela Project if its completion is delayed by more than 180 days, or more than 300 days in a force majeure event. Such a termination would not trigger the Google Backstop.
Source (primary)
terawulf 8-K exhibit (tm2528711d1_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-28)Live source ↗
Quote: “If completion of an Akela Project is delayed by greater than 180 days, or greater than 300 days in the case of a force majeure event, Fluidstack will have the right to terminate the applicable Fluidstack Lease”
How we checked this
Checked on September 30, 2026. The cited source supports every part of this claim.
The document sets out the 180-day and 300-day delay termination rights. It also states that such a termination would not trigger the Google Backstop.
Confirmed in the source:
- Fluidstack may terminate the lease for an Akela Project if its completion is delayed by more than 180 days.
- In a force majeure event, the delay threshold for Fluidstack's termination right is more than 300 days.
- A termination for such a delay would not trigger the Google Backstop.
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000110465925099345/tm2528711d1_ex99-1.htm) in full (24,367 characters, retrieved September 28, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (tm2528711d1_ex99-1.htm)
Quote: “If completion of an Akela Project is delayed by greater than 180 days, or greater than 300 days in the case of a force majeure event, Fluidstack will have the right to terminate the applicable Fluidstack Lease”