Fluidstack termination right on Akela Project delay

Company: TeraWulf - Project: Akela Data

Subject kind
customer
Statement date
2025-10-13
Current status
stated

The claim, verbatim

Fluidstack may terminate the lease for an Akela Project if its completion is delayed by more than 180 days, or more than 300 days in a force majeure event. Such a termination would not trigger the Google Backstop.

Source (primary)

terawulf 8-K exhibit (tm2528711d1_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-28)Live source ↗

Quote: “If completion of an Akela Project is delayed by greater than 180 days, or greater than 300 days in the case of a force majeure event, Fluidstack will have the right to terminate the applicable Fluidstack Lease”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (tm2528711d1_ex99-1.htm)

Quote: “If completion of an Akela Project is delayed by greater than 180 days, or greater than 300 days in the case of a force majeure event, Fluidstack will have the right to terminate the applicable Fluidstack Lease”

View cached copy (2026-09-28)Live source ↗