CB-1 colocation pilot targeted operational Q4 2024
Company: TeraWulf
What the later record shows
The date slipped · new target March 31, 2025
The October and November 2024 materials moved CB-1's operational target from Q4 2024 to Q1 2025. No passage confirms when it actually became operational.
“The CB-1 facility is on track to be operational in Q1 2025.”
2024-10-03 · terawulf 8-K exhibit (wulfopsreportsep2410-03x.htm) View cached copy (2026-10-26)Live source ↗
“CB-1 (20 MW) is on track for delivery in Q1 2025”
2024-11-11 · terawulf 8-K exhibit (wulfq32024investorpres11.htm) View cached copy (2026-10-25)Live source ↗
Checked October 31, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf is designing a 20 MW colocation pilot (CB-1) at Lake Mariner supporting 16 MW of critical IT load with liquid cooling and Tier 3-type redundancy, targeting operation in Q4 2024.
Source (primary)
terawulf 8-K exhibit (wulfjuly2024opsreport08-.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-31)Live source ↗
Quote: “TeraWulf is also designing a 20 MW colocation pilot project (“CB-1”) at the Lake Mariner facility capable of supporting 16 MW of critical IT load with liquid cooling and redundancy requirements typical of a Tier 3 data center, with a target operational date in Q4 2024.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (wulfjuly2024opsreport08-.htm)
Quote: “TeraWulf is also designing a 20 MW colocation pilot project (“CB-1”) at the Lake Mariner facility capable of supporting 16 MW of critical IT load with liquid cooling and redundancy requirements typical of a Tier 3 data center, with a target operational date in Q4 2024.”
delays terawulf 8-K exhibit (wulfq32024investorpres11.htm)
Quote: “CB-1 (20 MW) is on track for delivery in Q1 2025”
delays terawulf 8-K exhibit (wulfopsreportsep2410-03x.htm)
Quote: “The CB-1 facility is on track to be operational in Q1 2025.”