Project Akela capacity
Company: TeraWulf - Project: Akela Data
The claim, verbatim
Project 'Akela' consists of CB-3, CB-4 and CB-5 data centres with total gross capacity of 450 MW.
Source (primary)
TeraWulf Sustainable Finance Framework Second Party Opinion 2025 (IR page (investors.terawulf.com), ir_release)
View cached copy (2026-10-06)Live source ↗Archive.org ↗
Quote: “Project ‘Akela’ consists of CB-3, CB-4 and CB-5 data centres with a total gross capacity of 450 MW.”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The document states that Project Akela comprises CB-3, CB-4 and CB-5, with 450 MW total gross capacity.
Confirmed in the source:
- Project Akela consists of the CB-3, CB-4 and CB-5 data centres
- Project Akela has a total gross capacity of 450 MW
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2476/23465/pdf/TeraWulf_Sustainable_Finance_Framework_Second_Party_Opinion_2025.pdf) in full (29,307 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms TeraWulf Sustainable Finance Framework Second Party Opinion 2025
Quote: “Project ‘Akela’ consists of CB-3, CB-4 and CB-5 data centres with a total gross capacity of 450 MW.”