Lake Mariner Building 3 miner deployment
Company: TeraWulf - Project: Akela Data
What the later record shows
Delivered on time · happened February 29, 2024
Building 3 was fully energized in January 2024 (P3). February production rose 'due to full deployment of Building 3', and hashrate reached 7.9 EH/s by month-end February (P5).
“Achieved 7.1 EH/s of self‐mining in January with Building 3 (45 MW) at Lake Mariner fully energized”
2024-02-01 · terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm) View cached copy (2026-11-12)Live source ↗
“a 16% increase from January’s bitcoin production despite a shorter month, due to full deployment of Building 3 at Lake Mariner”
2024-03-03 · terawulf 8-K exhibit (wulffeb24opsreportdraft0.htm) View cached copy (2026-11-09)Live source ↗
Checked November 15, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf expects to deploy and energize 18,500 S19j XP miners in the operationally ready Building 3 at Lake Mariner in February 2024.
Source (primary)
terawulf 8-K exhibit (wulfdec23opsreport01-03x.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-15)Live source ↗
Quote: “Building 3 at the Lake Mariner facility is operationally ready with energization of additional 18,500 S19j XP miners expected in February 2024.”
How we checked this
Additional evidence
confirms terawulf 8-K exhibit (wulfdec23opsreport01-03x.htm)
Quote: “Building 3 at the Lake Mariner facility is operationally ready with energization of additional 18,500 S19j XP miners expected in February 2024.”
confirms terawulf 8-K exhibit (wulffeb24opsreportdraft0.htm)
Quote: “a 16% increase from January’s bitcoin production despite a shorter month, due to full deployment of Building 3 at Lake Mariner”
confirms terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm)
Quote: “Achieved 7.1 EH/s of self‐mining in January with Building 3 (45 MW) at Lake Mariner fully energized”