Lake Mariner Building 3 miner deployment

Company: TeraWulf - Project: Akela Data

Subject kind
facility timeline
Statement date
2024-01-02
Promised by
2024-02-29
Promised amount
18500.0 units
Current status
verified

What the later record shows

Delivered on time · happened February 29, 2024

Building 3 was fully energized in January 2024 (P3). February production rose 'due to full deployment of Building 3', and hashrate reached 7.9 EH/s by month-end February (P5).

“Achieved 7.1 EH/s of self‐mining in January with Building 3 (45 MW) at Lake Mariner fully energized”
2024-02-01 · terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm) View cached copy (2026-11-12)Live source ↗
“a 16% increase from January’s bitcoin production despite a shorter month, due to full deployment of Building 3 at Lake Mariner”
2024-03-03 · terawulf 8-K exhibit (wulffeb24opsreportdraft0.htm) View cached copy (2026-11-09)Live source ↗

Checked November 15, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

TeraWulf expects to deploy and energize 18,500 S19j XP miners in the operationally ready Building 3 at Lake Mariner in February 2024.

Source (primary)

terawulf 8-K exhibit (wulfdec23opsreport01-03x.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-15)Live source ↗

Quote: “Building 3 at the Lake Mariner facility is operationally ready with energization of additional 18,500 S19j XP miners expected in February 2024.”

How we checked this

Attempted on November 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330124000007/wulfdec23opsreport01-03x.htm) in full (11,186 characters, retrieved November 15, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (wulfdec23opsreport01-03x.htm)

Quote: “Building 3 at the Lake Mariner facility is operationally ready with energization of additional 18,500 S19j XP miners expected in February 2024.”

View cached copy (2026-11-15)Live source ↗

confirms terawulf 8-K exhibit (wulffeb24opsreportdraft0.htm)

Quote: “a 16% increase from January’s bitcoin production despite a shorter month, due to full deployment of Building 3 at Lake Mariner”

View cached copy (2026-11-09)Live source ↗

confirms terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm)

Quote: “Achieved 7.1 EH/s of self‐mining in January with Building 3 (45 MW) at Lake Mariner fully energized”

View cached copy (2026-11-12)Live source ↗

Record of changes

November 15, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 15, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 15, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.