CB-3 delivery at Lake Mariner
Company: TeraWulf
What the later record shows
Delivered late · happened July 31, 2026
CB-3 (42 MW) is listed as delivered in the Q2 2026 update, but total energized capacity was 81 MW at June 30, 2026 and 102 MW only as of July 2026. That implies about half of CB-3 was still pending after May, although the date is inferred from these totals and P25 refers to some CB-3 delivery in May.
“DELIVERED 102 MW ➢ WULF Den (2 MW) ➢ CB - 1 (16 MW) ➢ CB - 2A (21 MW) ➢ CB - 2B (21 MW) ➢ CB - 3 (42 MW)”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
“As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”
2026-08-04 · TeraWulf 10-Q filed 2026-08-05 View cached copy (2026-08-31)Live source ↗
“102 MW Energized and Generating Lease Revenue as of July 2026”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked November 5, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
CB-3, with 42 MW of critical IT capacity, is scheduled for delivery in May 2026.
Source (primary)
Q4 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-05)Live source ↗Archive.org ↗
Quote: “CB-3 (42 MW, May)”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Q4 Earnings Update Presentation
Quote: “CB-3 (42 MW, May)”
confirms TeraWulf 10-Q filed 2026-08-05
Quote: “As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”
confirms Q2 2026 Earnings Update Presentation
Quote: “DELIVERED 102 MW ➢ WULF Den (2 MW) ➢ CB - 1 (16 MW) ➢ CB - 2A (21 MW) ➢ CB - 2B (21 MW) ➢ CB - 3 (42 MW)”
