Lake Mariner customers

Company: TeraWulf - Project: Akela Data

Subject kind
customer
Statement date
2026-08-04
Promised by
2027-03-31
Promised amount
378.0 MW
Current status
stated

The claim, verbatim

Lake Mariner contracts: Core42 60 MW (Jul '25–Mar '26) and Fluidstack 378 MW (Jun '26–Mar '27).

Source (primary)

Q2 2026 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-06)Live source ↗Archive.org ↗

Quote: “60 MW Jul ’25 – Mar ’26 378 MW Jun ‘26 – Mar ’27”

How we checked this

Checked on October 13, 2026. The cited source supports part of this claim, but not all of it.

The presentation lists the 60 MW and 378 MW contracts and their delivery windows, but leaves the customer field blank on those contracts. It names Core42 and Fluidstack as Lake Mariner customers only in a chart legend, without explicitly pairing each name with a contract size.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2396/23522/pdf/TeraWulf+Q2+2026+Investor+Presentation.pdf) in full (28,349 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Q2 2026 Earnings Update Presentation

Quote: “60 MW Jul ’25 – Mar ’26 378 MW Jun ‘26 – Mar ’27”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

Record of changes

October 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-10-06 was the source's retrieval date; source published 2026-08-04.