Lake Mariner online capacity reaches 160 MW

Company: TeraWulf - Project: Akela Data

Subject kind
facility capacity
Statement date
2024-03-18
Promised amount
160.0 MW
Current status
stated

The claim, verbatim

Building 2 (50 MW) was energized in June 2023 and Building 3 (45 MW) was completed in December 2023, bringing online capacity at Lake Mariner to 160 MW.

Source (primary)

terawulf 8-K exhibit (exhibit991-earningsrelea.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-08)Live source ↗

Quote: “Building 3 (45 MW) was subsequently completed in December, bringing online capacity at the Lake Mariner facility to 160 MW”

How we checked this

Checked on November 10, 2026. The cited source supports every part of this claim.

The fiscal 2023 results section says Building 2 (50 MW) was energized in June and Building 3 (45 MW) was completed in December. It says this brought Lake Mariner's online capacity to 160 MW.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330124000066/exhibit991-earningsrelea.htm) in full (27,213 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (exhibit991-earningsrelea.htm)

Quote: “Building 3 (45 MW) was subsequently completed in December, bringing online capacity at the Lake Mariner facility to 160 MW”