$3.2B 7.75% senior secured green notes

Company: TeraWulf - Project: Akela Data

Subject kind
financing
Statement date
2025-11-10
Promised amount
3200000000.0 USD
Current status
stated

The claim, verbatim

On October 16, TeraWulf priced a $3.2 billion offering of 7.750% senior secured notes due 2030 at par, through WULF Compute LLC, to finance 522.5 MW of HPC data centers at Lake Mariner.

Source (primary)

Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-13)Live source ↗Archive.org ↗

Quote: “On October 16th, TeraWulf priced a $3.2 billion offering of 7.750% senior secured notes due 2030 at par”

How we checked this

Checked on October 15, 2026. The cited source supports every part of this claim.

The presentation states that on October 16 TeraWulf priced $3.2B of 7.750% senior secured notes due 2030 at par, issued by WULF Compute LLC, to finance 522.5 MW of HPC data centers at Lake Mariner.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_513c80c486e62e4bdb70115ded3782f5/terawulf/db/2396/23306/pdf/WULF_Q3_2025_Investor_Update_%28Nov_2025%29vF.pdf) in full (31,442 characters, retrieved October 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Investor Presentation

Quote: “On October 16th, TeraWulf priced a $3.2 billion offering of 7.750% senior secured notes due 2030 at par”