Lake Mariner Building 4 (35 MW) completion by mid-2024

Company: TeraWulf - Project: Akela Data

Subject kind
facility timeline
Statement date
2024-04-01
Promised by
2024-06-30
Promised amount
35.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

Building 4 was meant to take Lake Mariner from 160 MW to 195 MW, and the track-record chart shows Lake Mariner at 195 MW in 3Q 2024. The exact completion date relative to mid-2024 is not stated.

“with the addition of Building 4, which is expected to increase the facility’s bitcoin mining infrastructure capacity from its current 160 MW to 195 MW by mid 2024”
2024-05-12 · terawulf 8-K exhibit (aex991xearningsreleasexq12.htm) View cached copy (2026-11-06)Live source ↗
“3 MW 60 MW 60 MW 110 MW 195 MW 195 MW 225 MW 30 MW 50 MW 50 MW”
2025-05-08 · terawulf 8-K exhibit (wulfq12025investorpresvf.htm) View cached copy (2026-10-15)Live source ↗

Checked November 8, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Construction of the 35 MW Building 4 at Lake Mariner remains on track to be completed by mid-2024.

Source (primary)

terawulf 8-K exhibit (wulfmar24opsreport04-1x2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-08)Live source ↗

Quote: “Construction of Building 4 (35 MW) at the Lake Mariner facility remains on track to be completed by mid-2024”

How we checked this

Checked on November 10, 2026. The cited source supports every part of this claim.

The April 2, 2024 update states that construction of the 35 MW Building 4 at Lake Mariner remains on track for completion by mid-2024.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330124000082/wulfmar24opsreport04-1x2.htm) in full (9,459 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (wulfmar24opsreport04-1x2.htm)

Quote: “Construction of Building 4 (35 MW) at the Lake Mariner facility remains on track to be completed by mid-2024”

View cached copy (2026-11-08)Live source ↗

confirms terawulf 8-K exhibit (wulfq12025investorpresvf.htm)

Quote: “3 MW 60 MW 60 MW 110 MW 195 MW 195 MW 225 MW 30 MW 50 MW 50 MW”

View cached copy (2026-10-15)Live source ↗

confirms terawulf 8-K exhibit (aex991xearningsreleasexq12.htm)

Quote: “with the addition of Building 4, which is expected to increase the facility’s bitcoin mining infrastructure capacity from its current 160 MW to 195 MW by mid 2024”

View cached copy (2026-11-06)Live source ↗

Record of changes

November 8, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 8, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.