CB-3 and CB-4 initial delivery
Company: TeraWulf
What the later record shows
Delivered late · happened July 31, 2026
The 81 MW energized at June 30, 2026 implies only about 21 MW of CB-3 beyond the earlier 60 MW, short of 42 MW by the end of 1H 2026. CB-3's full 42 MW was listed as delivered with 102 MW energized as of July 2026; confidence is low because this relies on inference and the original slide's period alignment is unclear.
“As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”
2026-08-04 · TeraWulf 10-Q filed 2026-08-05 View cached copy (2026-08-31)Live source ↗
“102 MW Energized and Generating Lease Revenue as of July 2026”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-11-05)Live source ↗Archive.org ↗
“DELIVERED 102 MW ➢ WULF Den (2 MW) ➢ CB - 1 (16 MW) ➢ CB - 2A (21 MW) ➢ CB - 2B (21 MW) ➢ CB - 3 (42 MW)”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-11-05)Live source ↗Archive.org ↗
Checked November 6, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The cumulative delivery timeline for CB-3 and CB-4 shows 42 MW of critical IT load delivered by the first half of 2026; the slide text does not clearly align this figure to a single period.
Source (primary)
Q2 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗
Quote: “Cumulative Delivery Timeline 2H 2025 42 MW 1H 2026 200+ MW 2H 2026”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Q2 Earnings Update Presentation
Quote: “Cumulative Delivery Timeline 2H 2025 42 MW 1H 2026 200+ MW 2H 2026”
confirms TeraWulf 10-Q filed 2026-08-05
Quote: “As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”
confirms Q2 2026 Earnings Update Presentation
Quote: “102 MW Energized and Generating Lease Revenue as of July 2026”