CB-3 and CB-4 initial delivery

Company: TeraWulf

Subject kind
facility timeline
Statement date
2025-08-14
Promised by
2026-06-30
Promised amount
42.0 MW
Current status
verified

What the later record shows

Delivered late · happened July 31, 2026

The 81 MW energized at June 30, 2026 implies only about 21 MW of CB-3 beyond the earlier 60 MW, short of 42 MW by the end of 1H 2026. CB-3's full 42 MW was listed as delivered with 102 MW energized as of July 2026; confidence is low because this relies on inference and the original slide's period alignment is unclear.

“As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”
2026-08-04 · TeraWulf 10-Q filed 2026-08-05 View cached copy (2026-08-31)Live source ↗
“102 MW Energized and Generating Lease Revenue as of July 2026”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-11-05)Live source ↗Archive.org ↗
“DELIVERED 102 MW ➢ WULF Den (2 MW) ➢ CB - 1 (16 MW) ➢ CB - 2A (21 MW) ➢ CB - 2B (21 MW) ➢ CB - 3 (42 MW)”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-11-05)Live source ↗Archive.org ↗

Checked November 6, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The cumulative delivery timeline for CB-3 and CB-4 shows 42 MW of critical IT load delivered by the first half of 2026; the slide text does not clearly align this figure to a single period.

Source (primary)

Q2 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗

Quote: “Cumulative Delivery Timeline 2H 2025 42 MW 1H 2026 200+ MW 2H 2026”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Q2 Earnings Update Presentation

Quote: “Cumulative Delivery Timeline 2H 2025 42 MW 1H 2026 200+ MW 2H 2026”

View cached copy (2026-11-06)Live source ↗Archive.org ↗

confirms TeraWulf 10-Q filed 2026-08-05

Quote: “As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”

View cached copy (2026-08-31)Live source ↗

confirms Q2 2026 Earnings Update Presentation

Quote: “102 MW Energized and Generating Lease Revenue as of July 2026”

View cached copy (2026-11-05)Live source ↗Archive.org ↗

Record of changes

November 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 6, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.