CB-2B delivery at Lake Mariner

Company: TeraWulf

Subject kind
facility timeline
Statement date
2026-02-26
Promised by
2026-03-31
Promised amount
21.0 MW
Current status
verified

What the later record shows

Delivered on time · happened March 31, 2026

The Q1 2026 investor presentation lists CB-2B (21 MW) as delivered to date, as of March 31, 2026, which meets the Q1 2026 target.

“➢ CB-2A (21 MW) ➢ CB-2B (21 MW) DELIVERED TO DATE(1)”
2026-05-07 · terawulf 8-K exhibit (terawulfq12026investorpr.htm) View cached copy (2026-09-08)Live source ↗
“Capacity figures represent critical IT MWs. (1) As of March 31, 2026”
2026-05-07 · terawulf 8-K exhibit (terawulfq12026investorpr.htm) View cached copy (2026-09-08)Live source ↗
“60 MW of critical IT capacity energized and generating revenue as of March 31, 2026.”
2026-05-07 · terawulf 8-K exhibit (a_wulfearningsreleaseq1202.htm) View cached copy (2026-09-08)Live source ↗

Checked November 5, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

TeraWulf expects to deliver the 21 MW CB-2B capacity in Q1 2026.

Source (primary)

Q4 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-05)Live source ↗Archive.org ↗

Quote: “CB-2B: 21 MW expected to be delivered in Q1”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Q4 Earnings Update Presentation

Quote: “CB-2B: 21 MW expected to be delivered in Q1”

View cached copy (2026-11-05)Live source ↗Archive.org ↗

confirms terawulf 8-K exhibit (a_wulfearningsreleaseq1202.htm)

Quote: “60 MW of critical IT capacity energized and generating revenue as of March 31, 2026.”

View cached copy (2026-09-08)Live source ↗

confirms terawulf 8-K exhibit (terawulfq12026investorpr.htm)

Quote: “➢ CB-2A (21 MW) ➢ CB-2B (21 MW) DELIVERED TO DATE(1)”

View cached copy (2026-09-08)Live source ↗

Record of changes

November 5, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 5, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.