CB-2B delivery at Lake Mariner
Company: TeraWulf
What the later record shows
Delivered on time · happened March 31, 2026
The Q1 2026 investor presentation lists CB-2B (21 MW) as delivered to date, as of March 31, 2026, which meets the Q1 2026 target.
“➢ CB-2A (21 MW) ➢ CB-2B (21 MW) DELIVERED TO DATE(1)”
2026-05-07 · terawulf 8-K exhibit (terawulfq12026investorpr.htm) View cached copy (2026-09-08)Live source ↗
“Capacity figures represent critical IT MWs. (1) As of March 31, 2026”
2026-05-07 · terawulf 8-K exhibit (terawulfq12026investorpr.htm) View cached copy (2026-09-08)Live source ↗
“60 MW of critical IT capacity energized and generating revenue as of March 31, 2026.”
2026-05-07 · terawulf 8-K exhibit (a_wulfearningsreleaseq1202.htm) View cached copy (2026-09-08)Live source ↗
Checked November 5, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf expects to deliver the 21 MW CB-2B capacity in Q1 2026.
Source (primary)
Q4 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-05)Live source ↗Archive.org ↗
Quote: “CB-2B: 21 MW expected to be delivered in Q1”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Q4 Earnings Update Presentation
Quote: “CB-2B: 21 MW expected to be delivered in Q1”
confirms terawulf 8-K exhibit (a_wulfearningsreleaseq1202.htm)
Quote: “60 MW of critical IT capacity energized and generating revenue as of March 31, 2026.”
confirms terawulf 8-K exhibit (terawulfq12026investorpr.htm)
Quote: “➢ CB-2A (21 MW) ➢ CB-2B (21 MW) DELIVERED TO DATE(1)”