What the later record shows
Delivered late · happened July 31, 2025
HPC lease agreements were signed in December 2024, but the 10-Q says HPC leasing operations at Lake Mariner began in July 2025. That is after the promised 2024 start.
“In July 2025, TeraWulf commenced its HPC leasing operations and currently has energized 22.5 MW of HPC leasing capacity at the Lake Mariner Campus.”
2025-11-09 · TeraWulf 10-Q filed 2025-11-10 View cached copy (2026-08-31)Live source ↗
“In December 2024, the Company entered into long-term datacenter lease agreements (the “HPC Leases”) with a customer”
2026-08-04 · TeraWulf 10-Q filed 2026-08-05 View cached copy (2026-08-31)Live source ↗
Checked November 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf has committed a block of power at Lake Mariner, capable of deploying thousands of latest-generation GPUs, for a larger HPC project expected to commence in 2024.
Source (primary)
terawulf 8-K exhibit (terawulfincpressrelease1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-15)Live source ↗
Quote: “TeraWulf has initially committed a block of power at the Lake Mariner facility, capable of deploying thousands of latest generation GPUs, to support a larger HPC project expected to commence in 2024”
How we checked this
Additional evidence
confirms terawulf 8-K exhibit (terawulfincpressrelease1.htm)
Quote: “TeraWulf has initially committed a block of power at the Lake Mariner facility, capable of deploying thousands of latest generation GPUs, to support a larger HPC project expected to commence in 2024”
confirms TeraWulf 10-Q filed 2025-11-10
Quote: “In July 2025, TeraWulf commenced its HPC leasing operations and currently has energized 22.5 MW of HPC leasing capacity at the Lake Mariner Campus.”
confirms TeraWulf 10-Q filed 2026-08-05
Quote: “In December 2024, the Company entered into long-term datacenter lease agreements (the “HPC Leases”) with a customer”