WULF Den 2 MW AI/HPC proof-of-concept at Lake Mariner
Company: TeraWulf
What the later record shows
Delivered; the record does not say when
The October 3, 2024 release reports the 'recent completion' of the 2.5 MW (gross) HPC/AI proof-of-concept, which later materials call the 2.5 MW Wulf Den. No exact completion date is given, so it cannot be told whether it beat the early-September target.
“This includes the recent completion of a 2.5 MW (gross) HPC/AI digital infrastructure proof-of-concept project, designed to support both current and next-generation GPU technology.”
2024-10-03 · terawulf 8-K exhibit (wulfopsreportsep2410-03x.htm) View cached copy (2026-10-26)Live source ↗
“12-month revenue prepay for 2.5 MW Wulf Den, 20 MW CB-1 and 50 MW CB-2 at $1.5M per MW.”
2024-11-11 · terawulf 8-K exhibit (wulfq32024investorpres11.htm) View cached copy (2026-10-25)Live source ↗
Checked October 29, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf's 2 MW 'WULF Den' proof-of-concept project for WULF Compute at Lake Mariner, designed to house high-density GPUs, remains on track for completion in early September 2024; chillers and low-voltage transformers are installed and wiring and piping work is well underway.
Source (primary)
terawulf 8-K exhibit (wulfopsreport-202408aug2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-29)Live source ↗
Quote: “The project remains on track for completion in early September, with chillers and low-voltage transformers installed, and wiring and piping work to deliver power and cooling to the AI room well underway.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (wulfopsreport-202408aug2.htm)
Quote: “The project remains on track for completion in early September, with chillers and low-voltage transformers installed, and wiring and piping work to deliver power and cooling to the AI room well underway.”
confirms terawulf 8-K exhibit (wulfq32024investorpres11.htm)
Quote: “12-month revenue prepay for 2.5 MW Wulf Den, 20 MW CB-1 and 50 MW CB-2 at $1.5M per MW.”
confirms terawulf 8-K exhibit (wulfopsreportsep2410-03x.htm)
Quote: “This includes the recent completion of a 2.5 MW (gross) HPC/AI digital infrastructure proof-of-concept project, designed to support both current and next-generation GPU technology.”