CB-1 20 MW HPC facility completion in Q1 2025
Company: TeraWulf
What the later record shows
Delivered late · happened August 31, 2025
An August 2025 presentation says CB-1 would begin recording revenue in mid-August 2025, well after the Q1 2025 target. A July 2026 presentation lists CB-1 as delivered at 16 critical IT MW, which is presumably the critical IT figure for the 20 MW facility.
“x WULF Den began recording revenue in July x CB - 1 will begin recording revenue mid - August x CB - 2 on track for Q4 delivery”
2025-08-13 · terawulf 8-K exhibit (tm2523008d1_ex99-3.htm) View cached copy (2026-10-06)Live source ↗
“DELIVERED 102 MW ➢ WULF Den (2 MW) ➢ CB - 1 (16 MW) ➢ CB - 2A (21 MW)”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-10-06)Live source ↗Archive.org ↗
Checked October 24, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Dry cooler installation is complete for the 20 MW CB-1 HPC facility at Lake Mariner, which is on track for completion in Q1 2025.
Source (primary)
terawulf 8-K exhibit (wulfopsreport-202411nov2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-24)Live source ↗
Quote: “Dry cooler installation is complete for the 20 MW CB-1 facility, which is on track for Q1 2025 completion.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (wulfopsreport-202411nov2.htm)
Quote: “Dry cooler installation is complete for the 20 MW CB-1 facility, which is on track for Q1 2025 completion.”
confirms terawulf 8-K exhibit (tm2523008d1_ex99-3.htm)
Quote: “x WULF Den began recording revenue in July x CB - 1 will begin recording revenue mid - August x CB - 2 on track for Q4 delivery”
confirms Q2 2026 Earnings Update Presentation
Quote: “DELIVERED 102 MW ➢ WULF Den (2 MW) ➢ CB - 1 (16 MW) ➢ CB - 2A (21 MW)”