Lake Mariner 43 MW expansion completion

Company: TeraWulf - Project: Akela Data

Subject kind
facility timeline
Statement date
2023-10-02
Promised by
2023-12-31
Promised amount
43.0 MW
Current status
verified

What the later record shows

Delivered late · happened January 31, 2024

P3 says Building 3 (45 MW) at Lake Mariner was energized in January 2024, after the year-end 2023 target. No passage explicitly ties Building 3 to the '43 MW expansion,' and P5 says the site was running about 160 MW as of December 31, 2023, which conflicts on timing, so confidence is low.

“With the energization of Building 3 (45 MW) at the Lake Mariner facility in January, operational infrastructure capacity at the Lake Mariner facility increased to approximately 160 MW”
2024-02-01 · terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm) View cached copy (2026-11-12)Live source ↗
“The Lake Mariner Facility is operating approximately 160 MW of bitcoin mining capacity at the site as of December 31, 2023”
2024-03-19 · TeraWulf 10-K filed 2024-03-20 View cached copy (2026-09-13)Live source ↗

Checked November 19, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

TeraWulf's previously announced 43 MW expansion at the Lake Mariner facility is progressing and remains on target for completion by year-end 2023.

Source (primary)

terawulf 8-K exhibit (exhibit991-8xk.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-19)Live source ↗

Quote: “The previously announced 43 MW expansion at Lake Mariner is progressing and remains on target for completion by year-end 2023.”

How we checked this

Checked on November 21, 2026. The cited source supports every part of this claim.

The press release states almost word for word that the previously announced 43 MW Lake Mariner expansion is progressing and on target for completion by year-end 2023.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000162828023033562/exhibit991-8xk.htm) in full (9,047 characters, retrieved November 19, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (exhibit991-8xk.htm)

Quote: “The previously announced 43 MW expansion at Lake Mariner is progressing and remains on target for completion by year-end 2023.”

View cached copy (2026-11-19)Live source ↗

confirms TeraWulf 10-K filed 2024-03-20

Quote: “The Lake Mariner Facility is operating approximately 160 MW of bitcoin mining capacity at the site as of December 31, 2023”

View cached copy (2026-09-13)Live source ↗

confirms terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm)

Quote: “With the energization of Building 3 (45 MW) at the Lake Mariner facility in January, operational infrastructure capacity at the Lake Mariner facility increased to approximately 160 MW”

View cached copy (2026-11-12)Live source ↗

Record of changes

November 19, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 19, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.