CB-2 lease start date moved
Company: TeraWulf
What the later record shows
Delivered on time · happened March 31, 2026
CB-2A and CB-2B were both listed as delivered as of March 31, 2026, and the 60 MW energized by then was generating revenue, consistent with a Q1 2026 lease start. No passage states the CB-2 lease start date directly.
“➢ CB-2A (21 MW) ➢ CB-2B (21 MW) DELIVERED TO DATE(1)”
2026-05-07 · terawulf 8-K exhibit (terawulfq12026investorpr.htm) View cached copy (2026-09-08)Live source ↗
“60 MW of critical IT capacity energized and generating revenue as of March 31, 2026.”
2026-05-07 · terawulf 8-K exhibit (a_wulfearningsreleaseq1202.htm) View cached copy (2026-09-08)Live source ↗
Checked November 5, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The estimated lease start date for CB-2 moved from November 30, 2025 to Q1 2026.
Source (primary)
Q4 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-05)Live source ↗Archive.org ↗
Quote: “CB-2 11/30/25 Q1”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Q4 Earnings Update Presentation
Quote: “CB-2 11/30/25 Q1”
confirms terawulf 8-K exhibit (a_wulfearningsreleaseq1202.htm)
Quote: “60 MW of critical IT capacity energized and generating revenue as of March 31, 2026.”
confirms terawulf 8-K exhibit (terawulfq12026investorpr.htm)
Quote: “➢ CB-2A (21 MW) ➢ CB-2B (21 MW) DELIVERED TO DATE(1)”