60 MW energized at Lake Mariner
Company: TeraWulf - Project: Akela Data
The claim, verbatim
60 MW of critical IT capacity is energized and generating revenue (WULF Den, CB-1, CB-2A, CB-2B).
Source (primary)
Q1 2026 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-06)Live source ↗Archive.org ↗
Quote: “60 MW energized and generating revenue”
How we checked this
Checked on October 14, 2026. The cited source supports every part of this claim.
The deck says '60 MW energized and generating revenue,' and the serial-delivery slide lists the four delivered buildings, which sum to 60 MW of critical IT capacity as of March 31, 2026.
Confirmed in the source:
- 60 MW is energized and generating revenue
- Capacity delivered to date consists of WULF Den (2 MW), CB-1 (16 MW), CB-2A (21 MW) and CB-2B (21 MW), totaling 60 MW
- These capacity figures are critical IT MWs
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2396/23490/pdf/TeraWulf+Q1+2026+Investor+Presentation+%28May+2026%29.pdf) in full (27,753 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Q1 2026 Earnings Update Presentation
Quote: “60 MW energized and generating revenue”
confirms Q1 2026 Earnings Update Presentation
Quote: “60 MW energized and generating revenue”