Deployment of 18,500 S19j XP miners by Feb 1, 2024

Company: TeraWulf - Project: Akela Data

Subject kind
facility timeline
Statement date
2023-12-27
Promised by
2024-02-01
Promised amount
18500.0 units
Current status
verified

What the later record shows

Delivered; the record does not say when

The 10-K showed no S19j XP miners at Dec 31, 2023. The Q1 2024 10-Q lists 19,400 S19j XP miners owned by March 31, 2024, with 47,200 of 51,100 miners operational at Lake Mariner. No passage says whether the 18,500 were all deployed by February 1, 2024.

“As of March 31, 2024, we own approximately 51,100 miners of which approximately 47,200 are operational at the Lake Mariner Facility”
2024-05-12 · TeraWulf 10-Q filed 2024-05-13 View cached copy (2026-09-13)Live source ↗
“Bitmain S19j Pro 11,800 Bitmain S19j XP 19,400 Bitmain S19k Pro 1,600 MinerVA MV7 4,100”
2024-05-12 · TeraWulf 10-Q filed 2024-05-13 View cached copy (2026-09-13)Live source ↗

Checked November 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

TeraWulf estimates all 18,500 BITMAIN Antminer S19j XP miners will be deployed by February 1, 2024.

Source (primary)

terawulf 8-K exhibit (terawulfincpressrelease1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-15)Live source ↗

Quote: “Estimated deployment date of February 1, 2024, for all 18,500 BITMAIN Antminer S19j XP bitcoin miners.”

How we checked this

Attempted on November 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330123000066/terawulfincpressrelease1.htm) in full (8,845 characters, retrieved November 15, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (terawulfincpressrelease1.htm)

Quote: “Estimated deployment date of February 1, 2024, for all 18,500 BITMAIN Antminer S19j XP bitcoin miners.”

View cached copy (2026-11-15)Live source ↗

confirms TeraWulf 10-Q filed 2024-05-13

Quote: “As of March 31, 2024, we own approximately 51,100 miners of which approximately 47,200 are operational at the Lake Mariner Facility”

View cached copy (2026-09-13)Live source ↗

Record of changes

November 15, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 16, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 16, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.