Fluidstack data center lease
Company: TeraWulf - Project: Akela Data
The claim, verbatim
Akela entered into three data center lease agreements with Fluidstack in August 2025 to provide 378 MW of critical IT load, with construction commenced in 2025 and delivery expected to commence in 2026. Leases include substantial credit support from Google.
Source (primary)
TeraWulf 424B5 filed 2026-04-16 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “In August 2025, Akela entered into three data center lease agreements (the "Akela Fluidstack Leases") with Fluidstack USA I Inc....we will provide 378 MW of critical IT load...construction having commenced in 2025 and delivery expected to commence in 2026. The Akela Fluidstack Leases benefit from substantial credit support provided by Google”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms TeraWulf 424B5 filed 2026-04-16
Quote: “In August 2025, Akela entered into three data center lease agreements (the "Akela Fluidstack Leases") with Fluidstack USA I Inc....we will provide 378 MW of critical IT load...construction having commenced in 2025 and delivery expected to commence in 2026. The Akela Fluidstack Leases benefit from substantial credit support provided by Google”