Lake Mariner current operating capacity

Company: TeraWulf - Project: Akela Data

Subject kind
facility capacity
Statement date
2024-01-15
Promised amount
110.0 MW
Current status
stated

The claim, verbatim

Lake Mariner Facility is operating 110 MW of bitcoin mining capacity

Source (primary)

TeraWulf S-3/A filed 2024-01-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “As of the date of this prospectus, the Lake Mariner Facility is operating approximately 110 megawatt ("MW") of bitcoin mining capacity”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms TeraWulf S-3/A filed 2024-01-16

Quote: “As of the date of this prospectus, the Lake Mariner Facility is operating approximately 110 megawatt ("MW") of bitcoin mining capacity”