CB-1 critical IT load capacity
Company: TeraWulf
What the later record shows
The date slipped · new target September 30, 2025
One month after the claim, TeraWulf moved CB-1's operational target from year-end 2024 to Q1 2025. In May 2025 CB-1 (16 MW critical IT) was still listed as 'contracted' rather than operating, with Q3 2025 shown for CB-1. No passage confirms when CB-1 itself came online.
“The CB-1 facility is on track to be operational in Q1 2025.”
2024-10-03 · terawulf 8-K exhibit (wulfopsreportsep2410-03x.htm) View cached copy (2026-10-26)Live source ↗
“MB-5 40.0 50.0 40,000 operating WULF Den 2.0 2.5 6,000 contracted CB-1 16.0 20.0 61,000 contracted”
2025-05-08 · terawulf 8-K exhibit (wulfq12025investorpresvf.htm) View cached copy (2026-10-15)Live source ↗
“Q3 2025: 20 MW CB-1 ➢ Q4 2025: 50 MW CB-2 ➢ FYE 2026: incremental 177.5 MW (gross) expected to be available”
2025-05-08 · Investor Presentation View cached copy (2026-10-06)Live source ↗
Checked October 29, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
CB-1 is engineered to support 16 MW of critical IT load with liquid cooling and Tier 3-style redundancy, and remains on track to be operational by year-end 2024.
Source (primary)
terawulf 8-K exhibit (wulfopsreport-202408aug2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-29)Live source ↗
Quote: “This building is engineered to support 16 MW of critical IT load with liquid cooling and redundancy features typical of a Tier 3 data center, and it remains on track to be operational by year- end.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (wulfopsreport-202408aug2.htm)
Quote: “This building is engineered to support 16 MW of critical IT load with liquid cooling and redundancy features typical of a Tier 3 data center, and it remains on track to be operational by year- end.”
delays Investor Presentation
Quote: “Q3 2025: 20 MW CB-1 ➢ Q4 2025: 50 MW CB-2 ➢ FYE 2026: incremental 177.5 MW (gross) expected to be available”
delays terawulf 8-K exhibit (wulfq12025investorpresvf.htm)
Quote: “MB-5 40.0 50.0 40,000 operating WULF Den 2.0 2.5 6,000 contracted CB-1 16.0 20.0 61,000 contracted”
delays terawulf 8-K exhibit (wulfopsreportsep2410-03x.htm)
Quote: “The CB-1 facility is on track to be operational in Q1 2025.”