CB-1 critical IT load capacity

Company: TeraWulf

This claim was marked delayed on October 29, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility capacity
Statement date
2024-09-03
Promised by
2024-12-31
Promised amount
16.0 MW
Current status
delayed

What the later record shows

The date slipped · new target September 30, 2025

One month after the claim, TeraWulf moved CB-1's operational target from year-end 2024 to Q1 2025. In May 2025 CB-1 (16 MW critical IT) was still listed as 'contracted' rather than operating, with Q3 2025 shown for CB-1. No passage confirms when CB-1 itself came online.

“The CB-1 facility is on track to be operational in Q1 2025.”
2024-10-03 · terawulf 8-K exhibit (wulfopsreportsep2410-03x.htm) View cached copy (2026-10-26)Live source ↗
“MB-5 40.0 50.0 40,000 operating WULF Den 2.0 2.5 6,000 contracted CB-1 16.0 20.0 61,000 contracted”
2025-05-08 · terawulf 8-K exhibit (wulfq12025investorpresvf.htm) View cached copy (2026-10-15)Live source ↗
“Q3 2025: 20 MW CB-1 ➢ Q4 2025: 50 MW CB-2 ➢ FYE 2026: incremental 177.5 MW (gross) expected to be available”
2025-05-08 · Investor Presentation View cached copy (2026-10-06)Live source ↗

Checked October 29, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CB-1 is engineered to support 16 MW of critical IT load with liquid cooling and Tier 3-style redundancy, and remains on track to be operational by year-end 2024.

Source (primary)

terawulf 8-K exhibit (wulfopsreport-202408aug2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-29)Live source ↗

Quote: “This building is engineered to support 16 MW of critical IT load with liquid cooling and redundancy features typical of a Tier 3 data center, and it remains on track to be operational by year- end.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (wulfopsreport-202408aug2.htm)

Quote: “This building is engineered to support 16 MW of critical IT load with liquid cooling and redundancy features typical of a Tier 3 data center, and it remains on track to be operational by year- end.”

View cached copy (2026-10-29)Live source ↗

delays Investor Presentation

Quote: “Q3 2025: 20 MW CB-1 ➢ Q4 2025: 50 MW CB-2 ➢ FYE 2026: incremental 177.5 MW (gross) expected to be available”

View cached copy (2026-10-06)Live source ↗

delays terawulf 8-K exhibit (wulfq12025investorpresvf.htm)

Quote: “MB-5 40.0 50.0 40,000 operating WULF Den 2.0 2.5 6,000 contracted CB-1 16.0 20.0 61,000 contracted”

View cached copy (2026-10-15)Live source ↗

delays terawulf 8-K exhibit (wulfopsreportsep2410-03x.htm)

Quote: “The CB-1 facility is on track to be operational in Q1 2025.”

View cached copy (2026-10-26)Live source ↗

Record of changes

October 29, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 29, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.