CB-3 delivery May 2026
Company: TeraWulf - Project: Akela Data
What the later record shows
Delivered late · happened July 31, 2026
CB-3 was still nearing completion at the end of June 2026, and only 81 MW of HPC capacity was energized at that point. By July 2026 the company reported 102 MW energized, including CB-3 (42 MW), with CB-3 marked operational. That is after the May 2026 target.
“As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”
2026-08-04 · TeraWulf 10-Q filed 2026-08-05 View cached copy (2026-08-31)Live source ↗
“DELIVERED 102 MW ➢ WULF Den (2 MW) ➢ CB - 1 (16 MW) ➢ CB - 2A (21 MW) ➢ CB - 2B (21 MW) ➢ CB - 3 (42 MW)”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
“construction of a third building, CB-3, was nearing completion at quarter-end, with energization aligned with customer hardware deployment”
2026-08-16 · WULF Stock Swings After Earnings Miss – TeraWulf’s HPC Revenue Overtakes Bitcoin Mining - Stocktwits View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
CB-3 (42 MW) under construction, scheduled for May 2026 completion.
Source (primary)
Q1 2026 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-06)Live source ↗Archive.org ↗
Quote: “CB-3 (42 MW, May)”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The presentation lists CB-3 (42 MW, May) under construction and says CB-3 is on track for completion as part of its 2026 execution plan.
Confirmed in the source:
- CB-3 is listed as under construction
- CB-3 is 42 MW of critical IT capacity
- CB-3 is scheduled for completion in May (2026, per the 2026 execution slide stating CB-3 is on track for completion)
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2396/23490/pdf/TeraWulf+Q1+2026+Investor+Presentation+%28May+2026%29.pdf) in full (27,753 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Q1 2026 Earnings Update Presentation
Quote: “CB-3 (42 MW, May)”
confirms TeraWulf 10-Q filed 2026-08-05
Quote: “As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”
confirms WULF Stock Swings After Earnings Miss – TeraWulf’s HPC Revenue Overtakes Bitcoin Mining - Stocktwits
Quote: “construction of a third building, CB-3, was nearing completion at quarter-end, with energization aligned with customer hardware deployment”
confirms Q2 2026 Earnings Update Presentation
Quote: “DELIVERED 102 MW ➢ WULF Den (2 MW) ➢ CB - 1 (16 MW) ➢ CB - 2A (21 MW) ➢ CB - 2B (21 MW) ➢ CB - 3 (42 MW)”