CB-3 delivery May 2026

Company: TeraWulf - Project: Akela Data

Subject kind
facility timeline
Statement date
2026-05-14
Promised by
2026-05-31
Promised amount
42.0 MW
Current status
verified

What the later record shows

Delivered late · happened July 31, 2026

CB-3 was still nearing completion at the end of June 2026, and only 81 MW of HPC capacity was energized at that point. By July 2026 the company reported 102 MW energized, including CB-3 (42 MW), with CB-3 marked operational. That is after the May 2026 target.

“As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”
2026-08-04 · TeraWulf 10-Q filed 2026-08-05 View cached copy (2026-08-31)Live source ↗
“DELIVERED 102 MW ➢ WULF Den (2 MW) ➢ CB - 1 (16 MW) ➢ CB - 2A (21 MW) ➢ CB - 2B (21 MW) ➢ CB - 3 (42 MW)”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
“construction of a third building, CB-3, was nearing completion at quarter-end, with energization aligned with customer hardware deployment”
2026-08-16 · WULF Stock Swings After Earnings Miss – TeraWulf’s HPC Revenue Overtakes Bitcoin Mining - Stocktwits View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CB-3 (42 MW) under construction, scheduled for May 2026 completion.

Source (primary)

Q1 2026 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-06)Live source ↗Archive.org ↗

Quote: “CB-3 (42 MW, May)”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The presentation lists CB-3 (42 MW, May) under construction and says CB-3 is on track for completion as part of its 2026 execution plan.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2396/23490/pdf/TeraWulf+Q1+2026+Investor+Presentation+%28May+2026%29.pdf) in full (27,753 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Q1 2026 Earnings Update Presentation

Quote: “CB-3 (42 MW, May)”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms TeraWulf 10-Q filed 2026-08-05

Quote: “As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”

View cached copy (2026-08-31)Live source ↗

confirms WULF Stock Swings After Earnings Miss – TeraWulf’s HPC Revenue Overtakes Bitcoin Mining - Stocktwits

Quote: “construction of a third building, CB-3, was nearing completion at quarter-end, with energization aligned with customer hardware deployment”

View cached copy (2026-08-31)Live source ↗

confirms Q2 2026 Earnings Update Presentation

Quote: “DELIVERED 102 MW ➢ WULF Den (2 MW) ➢ CB - 1 (16 MW) ➢ CB - 2A (21 MW) ➢ CB - 2B (21 MW) ➢ CB - 3 (42 MW)”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

October 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 7, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-10-06 was the source's retrieval date; source published 2026-05-14.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.