jain.com

2 MW AI/HPC pilot at Lake Mariner

Company: TeraWulf

Subject kind
facility capacity
Statement date
2024-05-12
Current status
stated

The claim, verbatim

TeraWulf's 2024 capital plan includes capex for 2 MW of AI/HPC pilot infrastructure at the Lake Mariner facility.

Source (primary)

terawulf 8-K exhibit (wulfinvestorpresentation.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-06)Live source ↗

Quote: “Reflects capex associated with 2 MW AI/HPC pilot infrastructure at Lake Mariner facility”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (wulfinvestorpresentation.htm)

Quote: “Reflects capex associated with 2 MW AI/HPC pilot infrastructure at Lake Mariner facility”

View cached copy (2026-11-06)Live source ↗