Lake Mariner Building 4 completion

Company: TeraWulf - Project: Akela Data

Subject kind
facility timeline
Statement date
2024-01-02
Promised by
2024-06-30
Current status
verified

What the later record shows

Delivered late

Combined capacity was only 8.8 EH/s as of June 30, 2024 (P13), short of the ~10 EH/s promised for mid-2024. Lake Mariner later operated about 195 MW (160 MW plus Building 4's 35 MW) (P16), and the Q3 2024 presentation shows 10.0 EH/s (P17).

“As of June 30, 2024, these two industrial scale projects had a combined operating capacity of 8.8 EH/s with approximately 71,700 miners deployed”
2024-08-12 · TeraWulf 10-Q filed 2024-08-13 View cached copy (2026-08-31)Live source ↗
“As of the date of this Quarterly Report, the Company has a total operational bitcoin mining capacity of approximately 195 MW at the Lake Mariner Facility”
2024-11-11 · TeraWulf 10-Q filed 2024-11-12 View cached copy (2026-08-31)Live source ↗

Checked November 15, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Building 4 at Lake Mariner is under construction with planned completion in mid-2024, expected to bring total operational capacity to approximately 10 EH/s.

Source (primary)

terawulf 8-K exhibit (wulfdec23opsreport01-03x.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-15)Live source ↗

Quote: “Upon planned completion in mid-2024, Building 4 is expected to bring TeraWulf's total operational capacity to approximately 10 EH/s.”

How we checked this

Attempted on November 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330124000007/wulfdec23opsreport01-03x.htm) in full (11,186 characters, retrieved November 15, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (wulfdec23opsreport01-03x.htm)

Quote: “Upon planned completion in mid-2024, Building 4 is expected to bring TeraWulf's total operational capacity to approximately 10 EH/s.”

View cached copy (2026-11-15)Live source ↗

confirms TeraWulf 10-Q filed 2024-08-13

Quote: “As of June 30, 2024, these two industrial scale projects had a combined operating capacity of 8.8 EH/s with approximately 71,700 miners deployed”

View cached copy (2026-08-31)Live source ↗

confirms TeraWulf 10-Q filed 2024-11-12

Quote: “As of the date of this Quarterly Report, the Company has a total operational bitcoin mining capacity of approximately 195 MW at the Lake Mariner Facility”

View cached copy (2026-08-31)Live source ↗

Record of changes

November 15, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 15, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 15, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.