jain.com

Somerset data center acreage

Company: TeraWulf - Project: Akela Data

Subject kind
facility capacity
Statement date
2025-05-26
Promised amount
162.7 acres
Current status
stated

The claim, verbatim

TeraWulf leases approximately 162.7 acres in Somerset, New York for cryptocurrency mining and HPC data center operations

Source (primary)

TeraWulf 8-K filed 2025-05-27 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “consisting of approximately 162.7 acres”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms TeraWulf 8-K filed 2025-05-27

Quote: “consisting of approximately 162.7 acres”

View cached copy (2026-08-31)Live source ↗