CB-2 energization 1H2025

Company: TeraWulf

Subject kind
facility timeline
Statement date
2024-08-11
Promised by
2025-06-30
Promised amount
50.0 MW
Current status
verified

What the later record shows

Delivered late · happened March 31, 2026, new target December 31, 2025

CB-2 was retimed to Q4 2025, but only 18 critical IT MW were energized at year-end 2025. All 60 MW of Core42 leases (which include CB-2A and CB-2B) had commenced by March 31, 2026, so CB-2 was delivered late.

“Q2 2025: 2.5 MW WULF Den ➢ Q3 2025: 20 MW CB-1 ➢ Q4 2025: 50 MW CB-2”
2025-05-08 · Investor Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
“As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
“All of the Core42 Leases have commenced which comprised 60 critical IT MW HPC lease capacity as of March 31, 2026.”
2026-05-07 · TeraWulf 10-Q filed 2026-05-08 View cached copy (2026-08-31)Live source ↗
“DELIVERED 102 MW ➢ WULF Den (2 MW) ➢ CB - 1 (16 MW) ➢ CB - 2A (21 MW) ➢ CB - 2B (21 MW) ➢ CB - 3 (42 MW)”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked October 31, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CB-2, with 42 MW critical / 50 MW gross capacity, is expected to be energized in the first half of 2025.

Source (primary)

terawulf 8-K exhibit (ex992-wulfq22024investor.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-31)Live source ↗

Quote: “CB-2: 42 /50 MW (1)(2) expected to be energized in 1H25”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (ex992-wulfq22024investor.htm)

Quote: “CB-2: 42 /50 MW (1)(2) expected to be energized in 1H25”

View cached copy (2026-10-31)Live source ↗

confirms TeraWulf 10-Q filed 2026-05-08

Quote: “All of the Core42 Leases have commenced which comprised 60 critical IT MW HPC lease capacity as of March 31, 2026.”

View cached copy (2026-08-31)Live source ↗

confirms Q2 2026 Earnings Update Presentation

Quote: “DELIVERED 102 MW ➢ WULF Den (2 MW) ➢ CB - 1 (16 MW) ➢ CB - 2A (21 MW) ➢ CB - 2B (21 MW) ➢ CB - 3 (42 MW)”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms Investor Presentation

Quote: “Q2 2025: 2.5 MW WULF Den ➢ Q3 2025: 20 MW CB-1 ➢ Q4 2025: 50 MW CB-2”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms View 10-K PDF

Quote: “As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

October 31, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 31, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.