Lake Mariner Building 4 completion mid-2024 (~10 EH/s total)
Company: TeraWulf - Project: Akela Data
What the later record shows
Delivered; the record does not say when
In March 2024 Lake Mariner ran 160 MW and was building an additional 35 MW (Building 4). By November 2024 it reported about 195 MW operational, which implies Building 4 was finished. No passage gives the completion date, so whether it met mid-2024 cannot be told.
“is currently constructing an additional 35 MW at its Lake Mariner Facility, which is expected to be operational in mid-2024”
2024-03-19 · TeraWulf 10-K filed 2024-03-20 View cached copy (2026-09-13)Live source ↗
“the Company has a total operational bitcoin mining capacity of approximately 195 MW at the Lake Mariner Facility”
2024-11-11 · TeraWulf 10-Q filed 2024-11-12 View cached copy (2026-08-31)Live source ↗
Checked November 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Building 4 foundation is poured and construction is ongoing; completion is expected in mid-2024, bringing total operational capacity to approximately 10 EH/s.
Source (primary)
terawulf 8-K exhibit (terawulfincpressrelease1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-15)Live source ↗
Quote: “construction ongoing, which, upon completion in mid‐2024, will bring TeraWulf’s total operational capacity to ~10 EH/s”
How we checked this
Additional evidence
confirms terawulf 8-K exhibit (terawulfincpressrelease1.htm)
Quote: “construction ongoing, which, upon completion in mid‐2024, will bring TeraWulf’s total operational capacity to ~10 EH/s”
confirms TeraWulf 10-Q filed 2024-11-12
Quote: “the Company has a total operational bitcoin mining capacity of approximately 195 MW at the Lake Mariner Facility”
confirms TeraWulf 10-K filed 2024-03-20
Quote: “is currently constructing an additional 35 MW at its Lake Mariner Facility, which is expected to be operational in mid-2024”