Lake Mariner Building 4 completion mid-2024 (~10 EH/s total)

Company: TeraWulf - Project: Akela Data

Subject kind
facility timeline
Statement date
2023-12-27
Promised by
2024-06-30
Current status
verified

What the later record shows

Delivered; the record does not say when

In March 2024 Lake Mariner ran 160 MW and was building an additional 35 MW (Building 4). By November 2024 it reported about 195 MW operational, which implies Building 4 was finished. No passage gives the completion date, so whether it met mid-2024 cannot be told.

“is currently constructing an additional 35 MW at its Lake Mariner Facility, which is expected to be operational in mid-2024”
2024-03-19 · TeraWulf 10-K filed 2024-03-20 View cached copy (2026-09-13)Live source ↗
“the Company has a total operational bitcoin mining capacity of approximately 195 MW at the Lake Mariner Facility”
2024-11-11 · TeraWulf 10-Q filed 2024-11-12 View cached copy (2026-08-31)Live source ↗

Checked November 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Building 4 foundation is poured and construction is ongoing; completion is expected in mid-2024, bringing total operational capacity to approximately 10 EH/s.

Source (primary)

terawulf 8-K exhibit (terawulfincpressrelease1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-15)Live source ↗

Quote: “construction ongoing, which, upon completion in mid‐2024, will bring TeraWulf’s total operational capacity to ~10 EH/s”

How we checked this

Attempted on November 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330123000066/terawulfincpressrelease1.htm) in full (8,845 characters, retrieved November 15, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (terawulfincpressrelease1.htm)

Quote: “construction ongoing, which, upon completion in mid‐2024, will bring TeraWulf’s total operational capacity to ~10 EH/s”

View cached copy (2026-11-15)Live source ↗

confirms TeraWulf 10-Q filed 2024-11-12

Quote: “the Company has a total operational bitcoin mining capacity of approximately 195 MW at the Lake Mariner Facility”

View cached copy (2026-08-31)Live source ↗

confirms TeraWulf 10-K filed 2024-03-20

Quote: “is currently constructing an additional 35 MW at its Lake Mariner Facility, which is expected to be operational in mid-2024”

View cached copy (2026-09-13)Live source ↗

Record of changes

November 15, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 16, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 16, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.