CB-1 energization by YE2024
Company: TeraWulf
What the later record shows
The date slipped · new target March 31, 2025
Later 2024 materials pushed CB-1's delivery from year-end 2024 to Q1 2025. No passage confirms when it was energized.
“The CB-1 facility is on track to be operational in Q1 2025.”
2024-10-03 · terawulf 8-K exhibit (wulfopsreportsep2410-03x.htm) View cached copy (2026-10-26)Live source ↗
“CB-1 (20 MW) is on track for delivery in Q1 2025”
2024-11-11 · terawulf 8-K exhibit (wulfq32024investorpres11.htm) View cached copy (2026-10-25)Live source ↗
Checked October 31, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
CB-1, a 16 MW critical / 20 MW gross liquid-cooled HPC/AI building, is expected to be energized and substantially complete by year-end 2024.
Source (primary)
terawulf 8-K exhibit (ex992-wulfq22024investor.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-31)Live source ↗
Quote: “CB-1: 16/20 MW (1) capacity expected to be energized by YE24”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (ex992-wulfq22024investor.htm)
Quote: “CB-1: 16/20 MW (1) capacity expected to be energized by YE24”
delays terawulf 8-K exhibit (wulfq32024investorpres11.htm)
Quote: “CB-1 (20 MW) is on track for delivery in Q1 2025”
delays terawulf 8-K exhibit (wulfopsreportsep2410-03x.htm)
Quote: “The CB-1 facility is on track to be operational in Q1 2025.”