Lake Mariner Building 5 to add 50 MW in H2 2024

Company: TeraWulf

This claim was marked delayed on October 31, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility capacity
Statement date
2024-08-04
Promised by
2024-12-31
Promised amount
50.0 MW
Current status
delayed

What the later record shows

The date slipped · new target March 31, 2025

In November 2024 the additional 50 MW Lake Mariner facility was still under construction, with operation expected in Q1 2025 rather than H2 2024. Lake Mariner reached 245 MW (195 + 50) by August 2025, but no passage gives the completion date.

“is currently constructing an additional 50 MW facility, which we expect to be operational in the first quarter of 2025”
2024-11-11 · TeraWulf 10-Q filed 2024-11-12 View cached copy (2026-08-31)Live source ↗
“As of the date of this Quarterly Report, the facility is operating 245 MW of bitcoin mining capacity.”
2025-08-07 · TeraWulf 10-Q filed 2025-08-08 View cached copy (2026-08-31)Live source ↗

Checked October 31, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Construction has started on Building 5 at Lake Mariner, which is expected to add another 50 MW of infrastructure capacity in the second half of 2024.

Source (primary)

terawulf 8-K exhibit (wulfjuly2024opsreport08-.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-31)Live source ↗

Quote: “For the second half of 2024, construction has started on Building 5 at Lake Mariner, which is expected to add another 50 MW of infrastructure capacity.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (wulfjuly2024opsreport08-.htm)

Quote: “For the second half of 2024, construction has started on Building 5 at Lake Mariner, which is expected to add another 50 MW of infrastructure capacity.”

View cached copy (2026-10-31)Live source ↗

delays TeraWulf 10-Q filed 2024-11-12

Quote: “is currently constructing an additional 50 MW facility, which we expect to be operational in the first quarter of 2025”

View cached copy (2026-08-31)Live source ↗

delays TeraWulf 10-Q filed 2025-08-08

Quote: “As of the date of this Quarterly Report, the facility is operating 245 MW of bitcoin mining capacity.”

View cached copy (2026-08-31)Live source ↗

Record of changes

October 31, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 31, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.