WULF Den energization Sept 2024
Company: TeraWulf
What the later record shows
Delivered; the record does not say when
On 2024-09-03 the 2 MW proof-of-concept building was still under construction. The 2024-10-03 report says the 2.5 MW (gross) HPC/AI proof-of-concept project had recently been completed, which is the same scope later called Wulf Den. The passages do not say whether it was energized by September 30 or in the first days of October.
“This includes ongoing construction of a 2 MW AI/HPC digital infrastructure proof-of-concept building, designed to support both current and next-generation GPU technology.”
2024-09-03 · terawulf 8-K exhibit (wulfopsreport-202408aug2.htm) View cached copy (2026-10-29)Live source ↗
“This includes the recent completion of a 2.5 MW (gross) HPC/AI digital infrastructure proof-of-concept project, designed to support both current and next-generation GPU technology.”
2024-10-03 · terawulf 8-K exhibit (wulfopsreportsep2410-03x.htm) View cached copy (2026-10-26)Live source ↗
“12-month revenue prepay for 2.5 MW Wulf Den, 20 MW CB-1 and 50 MW CB-2 at $1.5M per MW.”
2024-11-11 · terawulf 8-K exhibit (wulfq32024investorpres11.htm) View cached copy (2026-10-25)Live source ↗
Checked October 31, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The WULF Den HPC/AI facility, with 2 MW critical / 2.5 MW gross capacity, is expected to be energized in September 2024.
Source (primary)
terawulf 8-K exhibit (ex992-wulfq22024investor.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-31)Live source ↗
Quote: “WULF Den: 2 /2.5 MW (1) capacity (2) expected to be energized in September 2024”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (ex992-wulfq22024investor.htm)
Quote: “WULF Den: 2 /2.5 MW (1) capacity (2) expected to be energized in September 2024”
confirms terawulf 8-K exhibit (wulfq32024investorpres11.htm)
Quote: “12-month revenue prepay for 2.5 MW Wulf Den, 20 MW CB-1 and 50 MW CB-2 at $1.5M per MW.”
confirms terawulf 8-K exhibit (wulfopsreportsep2410-03x.htm)
Quote: “This includes the recent completion of a 2.5 MW (gross) HPC/AI digital infrastructure proof-of-concept project, designed to support both current and next-generation GPU technology.”
confirms terawulf 8-K exhibit (wulfopsreport-202408aug2.htm)
Quote: “This includes ongoing construction of a 2 MW AI/HPC digital infrastructure proof-of-concept building, designed to support both current and next-generation GPU technology.”