Lake Mariner 500 MW deployed in 2025
Company: TeraWulf - Project: Akela Data
What the later record shows
The date slipped
By mid-2026, Lake Mariner had 145 MW of mining capacity and 81 critical IT MW of HPC energized. That is well short of 500 MW deployed in 2025.
“has energized 145 MW of capacity across three buildings and supporting infrastructure at the site”
2026-08-04 · TeraWulf 10-Q filed 2026-08-05 View cached copy (2026-08-31)Live source ↗
“As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”
2026-08-04 · TeraWulf 10-Q filed 2026-08-05 View cached copy (2026-08-31)Live source ↗
Checked November 8, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf targets 500 MW deployed at Lake Mariner in 2025.
Source (primary)
terawulf 8-K exhibit (exhibit992-wulfmarch24in.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-08)Live source ↗
Quote: “Target of 500 MW Deployed in 2025”
How we checked this
Checked on November 10, 2026. The cited source supports every part of this claim.
The Lake Mariner Data site summary lists a 'Target of 500 MW Deployed in 2025'.
Confirmed in the source:
- TeraWulf targets 500 MW deployed at Lake Mariner in 2025
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330124000066/exhibit992-wulfmarch24in.htm) in full (13,743 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (exhibit992-wulfmarch24in.htm)
Quote: “Target of 500 MW Deployed in 2025”
delays TeraWulf 10-Q filed 2026-08-05
Quote: “has energized 145 MW of capacity across three buildings and supporting infrastructure at the site”