Company is currently expanding Lake Mariner Facility with addition of third building for incremental 43 MW capacity
Source (primary)
TeraWulf S-3/A filed 2024-03-08 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “the Company is currently expanding its Lake Mariner Facility with the addition of a third building, which will house an incremental 43 MW of bitcoin mining capacity.”
How we checked this
Checked on September 21, 2026. The cited source supports every part of this claim.
The document expressly describes the third-building expansion and its 43 MW capacity.
Confirmed in the source:
- TeraWulf is expanding the Lake Mariner Facility with a third building
- The third building will house an incremental 43 MW of bitcoin mining capacity
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1083301/000108330124000058/terawulfincs-3a3tobefiled.htm) in full (101,409 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms TeraWulf S-3/A filed 2024-03-08
Quote: “the Company is currently expanding its Lake Mariner Facility with the addition of a third building, which will house an incremental 43 MW of bitcoin mining capacity.”