Lake Mariner Building 3 completion

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
facility timeline
Statement date
2023-09-04
Promised by
2023-12-31
Current status
verified

What the later record shows

Delivered late · happened January 31, 2024

As of September 30, 2023, only buildings one and two were described as substantially complete. Building 3 was energized in January 2024, about one month after the year-end 2023 target.

“construction activities at the Lake Mariner Facility for buildings one and two and the Nautilus Cryptomine Facility are substantially complete as of September 30, 2023”
2023-11-21 · TeraWulf 10-Q/A filed 2023-11-22 View cached copy (2026-09-13)Live source ↗
“With the energization of Building 3 (45 MW) at the Lake Mariner facility in January, operational infrastructure capacity at the Lake Mariner facility increased to approximately 160 MW”
2024-02-01 · terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm) View cached copy (2026-11-12)Live source ↗

Checked November 20, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

TeraWulf is building Building 3 at its Lake Mariner facility and targets completion by year-end 2023.

Source (primary)

terawulf 8-K exhibit (wulf-20230905xex99.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-20)Live source ↗

Quote: “Building 3 is targeted for completion by year-end 2023.”

How we checked this

Checked on November 21, 2026. The cited source supports every part of this claim.

The release states the company is expanding Lake Mariner with construction of Building 3, targeted for completion by year-end 2023.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330123000042/wulf-20230905xex99.htm) in full (8,113 characters, retrieved November 20, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (wulf-20230905xex99.htm)

Quote: “Building 3 is targeted for completion by year-end 2023.”

View cached copy (2026-11-20)Live source ↗

confirms TeraWulf 10-Q/A filed 2023-11-22

Quote: “construction activities at the Lake Mariner Facility for buildings one and two and the Nautilus Cryptomine Facility are substantially complete as of September 30, 2023”

View cached copy (2026-09-13)Live source ↗

confirms terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm)

Quote: “With the energization of Building 3 (45 MW) at the Lake Mariner facility in January, operational infrastructure capacity at the Lake Mariner facility increased to approximately 160 MW”

View cached copy (2026-11-12)Live source ↗

Record of changes

November 20, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 20, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.