jain.com

Lake Mariner bitcoin mining capacity

Company: TeraWulf

Subject kind
facility capacity
Statement date
2026-11-05
Promised amount
145.0 MW
Current status
stated

The claim, verbatim

As of September 30, 2026, TeraWulf had energized 145 MW of bitcoin mining capacity across three buildings at the Lake Mariner Data Campus.

Source (primary)

TeraWulf 10-Q filed 2026-11-06 (SEC EDGAR, sec_filing)
View cached copy (2026-11-07)Live source ↗

Quote: “has energized 145 MW of capacity across three buildings and supporting infrastructure at the site”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms TeraWulf 10-Q filed 2026-11-06

Quote: “has energized 145 MW of capacity across three buildings and supporting infrastructure at the site”

View cached copy (2026-11-07)Live source ↗