Additional 178 MW HPC capacity 2H 2025
Company: TeraWulf
What the later record shows
The date slipped
At December 31, 2025, Lake Mariner had energized only 18 critical IT MW of HPC capacity, far below an additional 178 MW in 2H 2025. The Fluidstack leases moved to 2026 and early 2027.
“As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity and remains on track to deliver additional contracted capacity”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
“one of the Fluidstack HPC Leases has partially commenced and the remaining Fluidstack HPC Leases are expected to commence in the second half of 2026 as well as in early 2027”
2026-08-04 · TeraWulf 10-Q filed 2026-08-05 View cached copy (2026-08-31)Live source ↗
Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
An additional 178 MW of HPC capacity is expected to be available at Lake Mariner in 2H 2025.
Source (primary)
terawulf 8-K exhibit (wulfq32024investorpres11.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗
Quote: “2H 2025: Additional 178 MW expected to be available”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (wulfq32024investorpres11.htm)
Quote: “2H 2025: Additional 178 MW expected to be available”
delays TeraWulf 10-Q filed 2026-08-05
Quote: “one of the Fluidstack HPC Leases has partially commenced and the remaining Fluidstack HPC Leases are expected to commence in the second half of 2026 as well as in early 2027”
delays View 10-K PDF
Quote: “As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity and remains on track to deliver additional contracted capacity”