CB-3 lease commencement
Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory
What the later record shows
The date slipped · new target May 31, 2026
No Fluidstack lease (which includes CB-3) had commenced by March 31, 2026, so the 1Q26 target was missed. CB-3 delivery was later given as May 2026.
“As of March 31, 2026, none of the Fluidstack HPC Leases had commenced.”
2026-05-07 · TeraWulf 10-Q filed 2026-05-08 View cached copy (2026-08-31)Live source ↗
“Continued progress across HPC development buildings, including delivery of CB-3 capacity in May 2026.”
2026-05-07 · terawulf 8-K exhibit (a_wulfearningsreleaseq1202.htm) View cached copy (2026-09-08)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf's WULF Compute model assumes lease commencement of building CB-3 in Q1 2026.
Source (primary)
terawulf 8-K exhibit (terawulf-disclosure2025x.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-29)Live source ↗
Quote: “CB-3 lease commencement in 1Q26”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The presentation's 'Key Model Assumptions' for the WULF Compute schedule state 'CB-3 lease commencement in 1Q26.'
Confirmed in the source:
- TeraWulf's WULF Compute financial model lists key assumptions for building lease commencements
- The model assumes lease commencement of building CB-3 in 1Q26 (Q1 2026)
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330125000087/terawulf-disclosure2025x.htm) in full (10,965 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (terawulf-disclosure2025x.htm)
Quote: “CB-3 lease commencement in 1Q26”
delays TeraWulf 10-Q filed 2026-05-08
Quote: “As of March 31, 2026, none of the Fluidstack HPC Leases had commenced.”
delays terawulf 8-K exhibit (a_wulfearningsreleaseq1202.htm)
Quote: “Continued progress across HPC development buildings, including delivery of CB-3 capacity in May 2026.”