CB-2 lease commencement
Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory
What the later record shows
The date slipped · new target December 31, 2026
The 10-K says only certain Core42 leases commenced in 2025 and the remainder are expected to commence in 2026, so full CB-2 lease commencement did not occur in 4Q25.
“60 critical IT MW with Core42, commenced in 2025 and commencing in 2026”
2026-02-25 · terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm) View cached copy (2026-09-13)Live source ↗
“Certain of the Core42 HPC Leases commenced in 2025 and the remainder of the HPC Leases are expected to commence in 2026.”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf's WULF Compute model assumes full lease commencement of building CB-2 in Q4 2025.
Source (primary)
terawulf 8-K exhibit (terawulf-disclosure2025x.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-29)Live source ↗
Quote: “Full CB-2 lease commencement in 4Q25”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The presentation's 'Key Model Assumptions' for the WULF Compute schedule state 'Full CB-2 lease commencement in 4Q25.'
Confirmed in the source:
- TeraWulf's WULF Compute financial model lists key assumptions for building lease commencements
- The model assumes full lease commencement of building CB-2 in 4Q25 (Q4 2025)
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330125000087/terawulf-disclosure2025x.htm) in full (10,965 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (terawulf-disclosure2025x.htm)
Quote: “Full CB-2 lease commencement in 4Q25”
delays View 10-K PDF
Quote: “Certain of the Core42 HPC Leases commenced in 2025 and the remainder of the HPC Leases are expected to commence in 2026.”
delays terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm)
Quote: “60 critical IT MW with Core42, commenced in 2025 and commencing in 2026”