CB-1 20 MW HPC/AI facility completion Q1 2025
Company: TeraWulf
What the later record shows
Delivered late
In May 2025, CB-1 was still only targeted for first revenue in Q3 2025, after the Q1 2025 promise. The February 2026 presentation reports Wulf Den and CB-1 delivered, but gives no exact date.
“Q2 2025: 2.5 MW WULF Den ➢ Q3 2025: 20 MW CB-1 ➢ Q4 2025: 50 MW CB-2”
2025-05-08 · Investor Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
“Construction Updates ➢ Wulf Den & CB-1 delivered (18 MW) ➢ CB-2A delivered (21 MW)”
2026-02-26 · Q4 Earnings Update Presentation View cached copy (2026-10-13)Live source ↗Archive.org ↗
Checked October 26, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Construction of CB-1, a 20 MW HPC/AI facility at Lake Mariner, is on track, with completion and operation expected in Q1 2025.
Source (primary)
terawulf 8-K exhibit (wulfopsreportsep2410-03x.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-26)Live source ↗
Quote: “Construction of CB-1, our 20 MW HPC/AI facility at Lake Mariner, is on track, with completion expected in Q1 2025.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (wulfopsreportsep2410-03x.htm)
Quote: “Construction of CB-1, our 20 MW HPC/AI facility at Lake Mariner, is on track, with completion expected in Q1 2025.”
confirms Investor Presentation
Quote: “Q2 2025: 2.5 MW WULF Den ➢ Q3 2025: 20 MW CB-1 ➢ Q4 2025: 50 MW CB-2”
confirms Q4 Earnings Update Presentation
Quote: “Construction Updates ➢ Wulf Den & CB-1 delivered (18 MW) ➢ CB-2A delivered (21 MW)”