Additional capacity availability 2H 2025
Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory
What the later record shows
Outcome not yet confirmed
No passage defines or tracks the 178 MW figure. At 2025 year-end the site ran 245 MW of mining (up from 195 MW) and 18 MW of HPC, which cannot be tied to the 178 MW scope.
“as of December 31, 2025 the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity and had 18 critical IT MW of HPC capacity”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Additional 178 MW of capacity expected to be available in the second half of 2025
Source (primary)
Nautilus Sale Announcement (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “Additional 178 MW expected to be available in 2H25”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The HPC timeline slide states that an additional 178 MW is expected to be available in 2H25.
Confirmed in the source:
- An additional 178 MW of capacity is expected to be available in the second half of 2025
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_0c87b48cb4d1c6967968c7d0c3e5933d/terawulf/db/2396/23300/pdf/WULF_Nautilus_Sale_Announcement_Deck_%2810-03-24%29vF.pdf) in full (14,394 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Nautilus Sale Announcement
Quote: “Additional 178 MW expected to be available in 2H25”