CB-1 revenue mid-August 2025
Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory
What the later record shows
Outcome not yet confirmed
Later filings show 18 critical IT MW of HPC capacity at December 31, 2025, but no passage specifically says CB-1 began recording revenue or when.
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Core42 building CB-1 at Lake Mariner will begin recording revenue in mid-August 2025.
Source (primary)
terawulf 8-K exhibit (tm2523008d1_ex99-3.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-06)Live source ↗
Quote: “CB - 1 will begin recording revenue mid - August”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The 2025 highlights slide lists CB-1 under delivering Core42 capacity and says it will begin recording revenue mid-August. The document places the Core42 lease at Lake Mariner.
Confirmed in the source:
- CB-1 will begin recording revenue in mid-August 2025
- CB-1 is part of delivering Core42 capacity
- Core42's lease is at Lake Mariner
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000110465925078086/tm2523008d1_ex99-3.htm) in full (18,636 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (tm2523008d1_ex99-3.htm)
Quote: “CB - 1 will begin recording revenue mid - August”