MB-5 Mining Expansion Online

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
facility timeline
Statement date
2025-05-08
Promised amount
50.0 MW
Event date
2025-04-30
Current status
stated

What the later record shows

Not a promise: a reported event · happened April 30, 2025

The May 8, 2025 statement reports that MB-5 had already come online in April 2025. The same-day 10-Q shows mining capacity at 245 MW, up from 195 MW plus 50 MW under construction.

“the Company is currently constructing an additional 50 MW, which we expect to be operational in the first quarter of 2025”
2024-11-11 · TeraWulf 10-Q filed 2024-11-12 View cached copy (2026-08-31)Live source ↗
“As of the date of this Quarterly Report, the facility is operating 245 MW of bitcoin mining capacity.”
2025-05-08 · TeraWulf 10-Q filed 2025-05-09 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

50 MW MB-5 mining capacity expansion to come online in April 2025

Source (primary)

Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “50 MW (MB-5) expansion online April 2025”

How we checked this

Checked on October 16, 2026. The cited source supports every part of this claim.

TeraWulf's Q1 2025 presentation lists a 50 MW MB-5 expansion online in April 2025 under its bitcoin mining operations and describes MB-5 as a miner building. The presentation is dated May 9, 2025 and reports the expansion as already online, which matches the claim's timing.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_0c87b48cb4d1c6967968c7d0c3e5933d/terawulf/db/2396/23301/pdf/WULF_Q1_2025_Investor_Pres_vF.pdf) in full (23,307 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Investor Presentation

Quote: “50 MW (MB-5) expansion online April 2025”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms Investor Presentation

Quote: “50 MW (MB-5) expansion online April 2025”

View cached copy (2026-10-13)Live source ↗Archive.org ↗

confirms terawulf 8-K exhibit (wulfq12025investorpresvf.htm)

Quote: “50 MW (MB-5) expansion online April 2025”

View cached copy (2026-10-15)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 2, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2025-05-08.
October 9, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.