jain.com

Lake Mariner Building 3 first Hydra pod installed

Company: TeraWulf

Subject kind
facility timeline
Statement date
2023-11-01
Current status
stated

The claim, verbatim

The first pod of Hydra racks at Lake Mariner Building 3 was installed in the week before the release.

Source (primary)

terawulf 8-K exhibit (pr-wulfoct23opsreportfinal.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-17)Live source ↗

Quote: “with the first pod of Hydra racks already installed earlier this week”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (pr-wulfoct23opsreportfinal.htm)

Quote: “with the first pod of Hydra racks already installed earlier this week”

View cached copy (2026-11-17)Live source ↗