CB-5 delivery at Lake Mariner
Company: TeraWulf
The claim, verbatim
CB-5 (168 MW critical IT) is under construction with delivery scheduled for Q4 2026.
Source (primary)
Q1 2026 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-05)Live source ↗Archive.org ↗
Quote: “CB-5 (168 MW, Q4)”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Q1 2026 Earnings Update Presentation
Quote: “CB-5 (168 MW, Q4)”