The claim, verbatim
Lake Mariner has 500 MW power available plus 250 MW pending regulatory approval, totaling 750 MW power capacity
Source (primary)
WULF Expands Fluidstack Deal (IR page (investors.terawulf.com), ir_release)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “500 MW power available, plus another 250 MW pending regulatory approval (750 MW total)”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The Lake Mariner site slide lists 500 MW of power available plus 250 MW pending regulatory approval, for 750 MW total. Elsewhere the document also lists Lake Mariner at 750 MW.
Confirmed in the source:
- Lake Mariner has 500 MW of power available
- Another 250 MW is pending regulatory approval
- Total power capacity is 750 MW
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_0c87b48cb4d1c6967968c7d0c3e5933d/terawulf/db/2396/23304/pdf/WULF_Expands_Fluidstack_Deal_August_2025.pdf) in full (11,936 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WULF Expands Fluidstack Deal
Quote: “500 MW power available, plus another 250 MW pending regulatory approval (750 MW total)”